|
Building
Demolition
By
Dr. Heng Li [bshengli@polyu.edu.hk] Tel: 2766 5879
1.
References
The
College of Estate Management, 1995, Technology - Module
4, London: The College of Estate Management
2.
Learning Objectives
'An
ability to carry out the demolition work in a safe and economical
manner."
3. Preliminary
Procedures
At
this moment, there are no legal requirements in Hong Kong for
plans and constructional details of buildings to be kept and handed
over with the building once constructed. Consequently, details
of the specification and constructional elements have to be established
largely by survey, tests and careful inspection To carry out demolition
safely and economically needs a great deal of experience and skill
and an excellent knowledge of building construction.
3.1
Preliminary Investigation
Demolition is a highly skilled and dangerous activity in terms
of damage to life and property and there are certain basic factors
to consider before a contract is placed:
-
The
demolition contractor should have ample experience of the
type of work to be offered;
-
Fully
comprehensive insurance against all risks must be maintained
at all times;
-
An experienced
supervisor should be continuously in charge of the work;
-
The
contract price should include all safety precautions included
in the relevant building regulations;
-
The
completion date should be realistic, avoiding and need to
take risks to achieve the date.
3.2
Preliminary Considerations
Demolition operations are the subject of strict legal controls
- there is a substantial body of legislation and a great deal
of case law relating to such operations. There may also be some
regulations which impose additional restrictions: for example,
action against nuisance such as noise and dust. The BSI Code
of Practice for Demolition BS 6187 exerts further influence,
in that if the demolition contractor does not observe the recommendation
of the Code, this may well influence a Court's decision as to
his liability in any legal proceedings.
3.3
General Site Provisions
-
Plant
and Equipment
Must
only be operated by skilled operators and must be regularly
serviced.
-
Protective
Clothing
Buildings
where chemicals have been stored or where asbestos, lead
paint, dust or fumes may be present will require specialized
protective clothing, e.g. respirators, helmets, goggles,
footwear, gloves, etc. Projecting nails, pieces of metal,
etc. resulting from demolition can cause accidents.
-
Shoring
and Underpinning
The
demolition contractor has a legal obligation to show technical
competence when carrying out the work. When removing sections
of the building which could have leave other parts unsafe,
adequate temporary supports and shoring etc. must be provided.
-
These
will need to be well signposted and clear warnings given
that demolition work is in progress. This may include
the necessity for some kind of lighting.
-
Sections
of the building must not be overloaded with debris either
on suspended floors or against party walls.
-
These
can affect safety. Strong winds or drifting snow against
unsafe walls, suspended floors etc. which are unpropped
may lead to collapse.
-
The
build-up of water can sometimes be hazardous.
-
An
crane heights etc. must be checked against the height
of any surrounding overhead cables to avoid damage and
cutting off supplies etc.
-
These
must be constructed and illuminated to the relevant building
regulations.
-
The
demolition site and any partially demolished buildings
must be properly secured against entry.
-
Should
be kept to a minimum by spraying with water when necessary.
-
Suppressors
and silencers, particularly on compressors etc., should
be used to keep noise levels to a minimum.
3.4
Supervision of Demolition Work
A method statement showing how the demolition work is to be carried
out should be prepared and the contractors should appoint a "competent
person" to supervise the demolition work.
4.
Demolition
Processes
As
an intrinsic part of the construction process, efficient demolition
of structures is an important factors deserving careful consideration
in the evolution of any redevelopment project.
Modern
emphasis is on reduction of construction periods to ensure economic
redevelopment, coupled with increasing town centre regenerating
calling for careful demolition on constructed and restricted site,
have resulted in more consideration being given to demolition
as part of the process of construction and redevelopment than
was typical in previous times.
4.1
Developing a Demolition Strategy
The strategy will need to take into account the method of construction
used for the original building and its proximity to other buildings,
structures and the general public. These factors, together with
location, the cost and availability of tipping and disposal and
the desirability and economics of reuse, must be taken into account
in the development of an appropriate strategy for the demolition
of a structure.
4.2
Building Information
Information on buildings in terms of "as built" drawings and structural
details may often be unavailable or unreliable, and consequently
some investigative site and desk work may be necessary, both to
ascertain the way in which the building was originally constructed,
and to identify the stresses and strains which exist within it.
In
order to plan the most efficient method of demolition, it is important
to have a full understanding of the method of construction and
the stress patterns imposed upon the building. Failure to do so
may result in risks to the safety of both those involved in the
demolition and those in close proximity to the site.
4.3
Selecting Appropriate Techniques
Majors factors to be considered in selecting an appropriate technique
include:-
Safety of personnel and public
Working methods
Legislation applicable
Insurance cover
4.4
Preliminary Aspects Prior to Site Demolition Work
Considerations should be given to:-
-
Conducting
a site and building survey, with a structural bias;
-
The
examination of drawings and details of existing construction
where available;
-
The
preparation of details and drawings from site survey activities
where no such information is available;
-
Establishing
previous use of premises, especially with regard to flammable
substances or substances hazardous to health or safety;
-
Programming
the sequence of demolition work;
-
The
preparation of a Method Statement.
4.4.1
Method statement
-
A
detailed health and safety method statement, produced before
work starts, is essential for safe working. It should include
a full risk assessment, identify problems and their solutions,
and form a reference for the site supervision.
5.
Demolition Methods
In
many circumstances, buildings and structures should be demolished
in the reverse order to their erection, although where partial
demolition is involved a more careful evaluation of the nature
of the effects of the demolition is necessary.
Normally,
the demolition contractor is able to adopt a method of work which:-
-
gradually
reduces the height of the building; or
-
arranges
the deliberate controlled collapse of the building or structure
so that work can be completed at ground level.
5.1
Demolition Technique Selection The
choice of demolition technique will depend on the nature of the
building or structure and its environment. Risks to the public,
operatives involved in the demolition process and adjacent structures
and buildings should be considered.
Demolition
techniques may be categorized as:-
5.1.1
Piecemeal Demolition by Hand
Demolition
of buildings or structure by hand-held tools such as electric
or pneumatic breakers, sometimes as a preliminary to using other
methods, should be carried out, where practicable, in the reverse
order to the original construction sequence. Lifting appliances
may be necessary to hold larger structural members during cutting
and for lowering severed structural members and other debris.
Chutes may be used to discharge debris into a vehicle or hopper.
Foundations would normally be grubbed up by excavation machines.

Figure
1: Piecemeal demolition
5.1.2
By Machine
Simple
roof structures supported on wall plates should normally be demolished
to the level of wall plates by hand, but if this may involve unsafe
working, then demolition totally by machine may be appropriate.
Where
a building that is to be demolished by machine is attached to
another structure, the two properties should be separated by the
use of hand methods before the main demolition process begins.
When
any part of a building is being demolished by a balling machine,
pusher arm or similar equipment, only the machine operator and
banksman should be allowed close to the working area. The cabs
of all machines should be strong enough to protect the operator
against the fall of debris. In particular, the windscreen and
rooflight should be of shatterproof material and guarded by a
grille of steel bars or a substantial mesh.
-
Balling Machine
Balling
machines generally comprise a drag-line type crawler chassis
fitted with a lattice crane jib. The demolition ball, with
a steel anti-spin device, is suspended from the lifting rope
and swung by the drag rope.
Balling
should only carried out by skilled operatives under the control
of experienced supervisors using well maintained machines
adequate for the proposed duty and standing on a firm, level
base.
The
manufacturer should be consulted before a machine is used
for balling to establish any restrictions on the type or length
of jib or the weight of the ball.
Balling
operations subject cranes to dynamic stresses and wear, and
the ball chosen should have the minimum weight necessary for
effective use. In many cases, demolition balls of quite light
weight will be adequate.
Floors
should be demolished by dropping the ball on the highest remaining
floor and allowing the debris to fall inside the building. The
debris should be removed regularly to prevent excessive weight
accumulating on the lower floors.
Walls
or columns can be demolished either by swinging the ball in
line with the stationary jib, using the drag rope, or by slewing
the jib. The ball should not swung by derricking the jib.

Figure
2: Demolition ball
-
Hydraulic
Pusher Arm
Articulated,
hydraulically-powered pusher-arm machines are normally mounted
on a tracked or wheeled chassis, and have a toothed plate
or hook for applying for applying a horizontal force to a
wall. The machine should stand on a firm level base and apply
force by a controlled movement of the pusher arm.

Figure
3: Hydraulic pusher arm
-
Explosives
If
explosives are to be used for demolition, the planning and
execution, include pre-weakening, should be under the control
of a person competent in these techniques. For large demolition,
the competent person is likely to be an experienced explosive
engineer; for smaller work, a shot-firer may be sufficient.
When
the use of explosives is contemplated, it is usual to employ
a technique that will ensure the total demolition of the whole
building by staging a controlled collapse. The explosive charges
are set and fired in a sequence that will weaken the structure
in such a way that the building collapses in upon itself.
Although
we tend to think of explosives as devices producing spectacular
bomb-like explosions, the use of non-explosive "explosives"
is now at an advanced stage. These non-explosive techniques
are essentially expanding charges that achieve the same results
as explosives but without the noise and initial devastating
blast.
-
Overturning
- Wire Rope Pulling
This
method is the application of a horizontal force at a high
level by pulling with wire ropes attached to winches or vehicles,
and allowing the impact on overturning to demolish the building
or structure. An adequate steel cab or cage should protect
the winch or the pulling vehicle and the operator.
Building
over 21m high should not normally be demolished by rope pulling.
-
Impact
Hammer and Nibblers
Impact hammers
normally have a track- or wheel- mounted chassis, an articulated
boom, and a heavy duty pick vibrated by hydraulic or pneumatic
power to demolish concrete or masonry.
Nibblers
use a rotating action to snap brittle materials such as concrete
or masonry. In either case, material should be removed from
the top of walls or columns in courses not greater than 600mm
in depth, steel reinforcement should be cut separately as necessary.

Figure
5: Nibblers
5.2
Pre-Weakening
Buildings
and structures normally have structural elements designed to carry
safely the loading likely to be imposed during their life.
As
a preliminary to a deliberate controlled collapse, after loads
such as furnishings, plant and machinery have been removed, the
demolition contractor may be able to weaken some structural elements
and remove those new redundant. This pre-weakening is essentially
a planned exercise and must be preceded by an analysis of its
possible effects on the structure until it collapses, to ensure
that the structural integrity of the building is not jeopardized
accidentally. Insufficient information and planning relating to
the structure may result in dangerous and unsafe work.
5.3
Deliberate Controlled Collapse The
deliberate collapse of the whole or part of a building or structure
requires particularly high standards of planning, supervisions
and execution, and careful consideration of its effect on other
parts of the structure or on adjacent buildings or structures.
A surrounding clear area and exclusion zone are required to protect
both personnel and property from the fall of the structure itself
and debris which may be thrown up by the impact.
The
collapse is usually achieved either by removing key structural
elements (e.g. with explosive charges) or by wire rope pulling
at a high level to overturn the structure. The possible modes
of failure must be studied to ensure that the method selected
will produce the required pattern of collapse. If the operation
is not successful, the remaining structure may be extremely dangerous
for the completion of the demolition.
Demolition
by deliberate controlled collapse is not usually appropriate for
prestressed concrete except for simple pre-tensioned floor planks
or slabs.
|