Site
Planning
By
Dr. Heng Li [bshengli@polyu.edu.hk] Tel: 2766 5879
1.
Learning Objectives
"An
analysis of the factors affecting the decisions during contract
planning stage."
2.
Contract Planning and Control
This
involves working out a plan of campaign or a programme for the
contract as a whole and assembling the necessary data. Programme
is required to promote the satisfactory organization and flow
of the various building operations during the course of erection,
by planning in advance the times and sequences of all operations
and the requirements in labour, materials and equipment.
BRE
Digest 91 states a well planned programme should:-
-
show
the quickest and cheapest method of carrying out the work
-
ensure
continuous productive work for all operatives employed and
reduce unproductive time to a minimum
-
provide
an assessment of the level of productivity
-
determine
attendance dates and periods for all subcontractors’ work
-
provide
information on material quantities and essential delivery
dates, the quantity and capacity of the plant and the periods
it will be on site
-
provide
a simple and rapid method of measuring progress
2.1
Gantt Chart or Bar Chart
simple
and easily read plan of operations
plot
all site personnel against actual performances
only
takes into account one of the resources, time
does
not inform on the critical relationships between the various
activities
2.2
Critical Path Diagrams
2.3
Master Programme
-
On
acceptance of the tender, contract planning commences and
a working, or overall, programme is prepared.
-
This
is a guide for site activities, for detailed planning, for
the buying and delivery of materials, for the co-ordination
of sub-contractors’ and main contractor’s work and for assessing
job progress.
-
The
programme shows the major operations and phasing of the
job, but detailed short-term planning at regular intervals
on the site is necessary to ensure the satisfactory allocation
of labour and materials to each individual operation as
the work proceeds.
The
preparation of the overall programme consists broadly of:-
-
breaking
the job down into a series of basic operations involving
only one trade
-
establishing
the quantities of work in each operation and the time content
-
arranging
the operations in a sequence and balancing the size of gangs
to give a maximum continuity of work and minimum delay
-
breaking
down a large job into phases so that several operations
may proceed simultaneously.
3.
Planning Consideration
3.1
Site Conditions and Access
-
Site
conditions will limit the type of plant that may be used.
-
Wet
sites: need to use tracked machines in the case of excavators
and mobile cranes, and dumpers for transport
-
Sloping
sites: make the use of rail mounted cranes unsuitable or
uneconomical
-
Confined
sites: insufficient room for a mixer or mixing plant and
may need to use truck mixed concrete
-
Site
closely surrounded by tall adjoining buildings: indicate
the use of a derricking jib crane rather than a horizontal
jib crane in order to be able to rise and clear the buildings
-
Limitation
of access
3.2
Nature of Job
Different
type of structure and form, size and detailing of the building
will have effect upon the way the contract is planned.
Influence
the decision of equipment and materials.
3.3
Plant
General
considerations: capabilities, limitations and outputs of different
types of plants
Excavation
plants:
The
type of excvation to be carried out
The
nature of the soil to be excavated
The
volume of soil to be excavated
The
length of haul to tip and the terrain over which the
machinery has to dig and travel.
Handling:
Quantity
and nature of materials to be handled
Degree
of tower crane’s utilization
Avoid
"Double Handling:
Sitting
of hoisting plant, materials dumps and mixing plant
in relation to the building and to each other
Mixing:
Quality
and quantity of concrete required
Site
conditions
Costs
comparisons among various methods
Type
of Plant:
Nature
of job
Sequence
of work
Method
of construction
Amount
of work
Cost
of equipment and running cost
3.5
Design Factors
Simplicity
of construction and detailing
Separation
of trades
Phasing
of works
Continuity
of works
4.
Site Organization
4.1
Site Planning
Period
Planning – usually done monthly
Weekly
Planning – prepare towards the end of each week progress and
to plan the next week progress
Progress
Control – a regular review of the progress of all operations
and comparison with the programme or plan
4.2
Site Layout
Site
layout is divided into Administrative Area and Construction
Area.
Administrative
Area
-
Includes
stores, offices, sub-contracts’ huts, canteen and similar
accommodations
-
Locate
with quick access to the site area for control reasons
-
Ease
of connectivity in telephone facilities for communication,
electricity for power, compressed air for equipment, as
well as lighting and heating facilities for office huts
-
Careful
initial site planning is required to minimize to moving
of administrative area during the contract period
Construction
Area
-
Includes
the actual site of the buildings being constructed, materials
and equipment
-
Positioned
to minimize the time of handling and movement
-
Areas
properly identified beforehand to avoid the possibility
of dumping materials in the wrong position